Guildford West Responsible Planning Take action ↓

132 McCredie Road, Guildford West · SSD-69223466

StopProjectPluto

A $1.11 billion data centre has been approved 145 metres from our homes and 20 metres from Guildford West Sports Ground, and almost nobody here knew it was coming. Construction can’t start until the NSW Government approves the construction plans. That’s our window.

  • Approved 23 Jul 2026
  • Construction plans not yet approved

We’re not against jobs or technology. We’re against a 100-megawatt data centre with diesel backup generators 145 metres from homes, approved before most of us knew it existed.

How close is it?

The site is 20 metres from Guildford West Sports Ground and 145 metres from the nearest homes, about one and a half rugby league fields. Drawn to scale; distances from the project’s planning documents.

From the signed consent, 23 July 2026

What’s been approved

100 MW
of power, running 24 hours a day, seven days a week.
Consent A6, B1
170 MW
of diesel backup generators, with up to 2,000 tonnes of diesel stored on site.
Consent A6, A7
173 hours
a year the generators can run outside blackouts. Testing is allowed 7am–6pm Monday to Saturday and 8am–6pm on Sunday.
Consent A7, B1
4.8 ML
of water a day at peak for 26 cooling towers, nearly two Olympic pools. Recycled water is required only where it’s available.
Project documents and consent
No limit
on noise at homes during unplanned blackouts. Otherwise the limit is 37–40 dB(A), rising to 46–49 while the generators run.
Consent B7
25.8 m
tall: two three-storey buildings holding nine data halls.
Project documents
3 years
of construction, with more than 200 vehicle trips a day estimated.
Department assessment
TBC
is all Appendix 2 says. It should list the measures Goodman must take, and three conditions rely on it.
Consent A2, B3, B59

From Goodman’s own consultation report

Almost nobody knew

Goodman and the Department say the neighbourhood was told. Goodman’s own report shows how little of it got through.

1,194
homes and businesses got Goodman’s newsletter in their letterbox, three times between June 2024 and February 2025.
EIS Appendix E, p. 15
0
pieces of feedback from residents or local businesses through its 1800 number or project email, in the 41 weeks they were open.
EIS Appendix E, pp. 15, 31
3
responses to its online survey, and only one of them was complete.
EIS Appendix E, p. 16
2,000+
people signed a residents’ petition once the news got out, three months after approval.
Residents’ petition, Oct 2026

That’s not a neighbourhood that didn’t care. It’s one that didn’t know.

How it happened

  1. The Department sets the requirements for Goodman’s environmental assessment.

  2. The plans sit on the NSW Planning Portal for 28 days. Almost nobody hears about it.

  3. Approved by a senior Department officer on the Planning Minister’s behalf.

  4. Residents start hearing about it in the news, three months after it was approved.

  5. The construction plans still need approval. No work can start until they get it.

Lane Cove knew in time

Lane Cove West residents heard about Goodman’s Project Mars while it was still being assessed. They made 374 public submissions, a record for a NSW data centre according to Lane Cove Council, and in September 2026 Goodman withdrew it, citing community feedback among its reasons.

Project Mars

Lane Cove West · 90 MW

Withdrawn

September 2026

Residents knew in time

Project Pluto

Guildford West · 100 MW

Approved

July 2026

Almost nobody knew

Guildford West never got that chance. Construction hasn’t started, so there’s still time to be heard.

What we’re asking for

No construction until these are in place.

  1. Publish the missing measures. Complete Appendix 2 and let residents comment before any construction plan is approved.

  2. Recycled water only. Cooling towers should run on recycled water, not drinking water.

  3. Tighter generator rules. Fewer hours, no testing on hot or poor-air days, and a public log of every run.

  4. Independent noise monitoring. Live, published readings at homes and the sports ground, with limits that apply during blackouts too.

  5. A community committee. Residents, sports clubs, Council and Goodman, meeting from before construction starts.

  6. Safe construction. Trucks kept away from homes and schools, and no noisy work during weekend sport.

  7. A buffer in law. A minimum distance between data centres and homes, schools and sports grounds.

Takes two minutes

Email the people who decide

Pick what worries you and add a line in your own words. A personal line makes your email much harder to ignore.

What worries you most?
Send it to

Live outside the Granville electorate? Find your state MP and add them.

To
Subject

          

For the Minister, copy the email and paste it into the online form. Nothing you type leaves this page; the email goes from your own inbox, with a copy to the group if you leave that box ticked.

Show up

Three dates matter most. Turn up in person, or watch online.

Wed 18 Nov

6:30pm

Cumberland Council meeting

Council Chambers, 16 Memorial Avenue, Merrylands. Fill the public gallery. To speak, register by 5pm on Tuesday 17 November.

Thu 19 Nov

10am

Goodman Group AGM

InterContinental Sydney, 16 Phillip Street, and online. Anyone can watch the webcast as a guest; securityholders can ask questions.

Tell your street

Most people around the site still don’t know. Send this to your group chats, sports clubs and school parents.

WhatsApp Facebook